Me page does not show accepted tasks whether planned, started, completed

Created: 23/Jul/05 11:54 PM   Updated: 30/Nov/05 02:23 AM
Component/s: None
Affects Version/s: 0.7
Fix Version/s: 0.7

Time Tracking:
Original Estimate: 6 hours
Original Estimate - 6 hours
Remaining Estimate: 3 hours
Time Spent - 3 hours Remaining Estimate - 3 hours
Time Spent: 3 hours
Time Spent - 3 hours Remaining Estimate - 3 hours

File Attachments: 1. Zip Archive xpr-43-patches-untested.zip (6 kb)

Environment:
Issue Links:
Supercedes
 
dependent
 


 Description  « Hide
admin user accepts a 1 hr task in a 1h story => Me view shows "No planned tasks"
admin user enters time => Me view shows "No tasks in progress"
admin user complete task => Me view shows "No completed tasks"

 All   Comments   Work Log   Change History      Sort Order: Ascending order - Click to sort in descending order
Jacques Morel - 25/Aug/05 08:51 AM
James,
Where are you on this? We are starting to work on XPR-40 and would need your updates ASAP.
Thanks

James Beard - 28/Aug/05 08:32 AM
Changes to date. Untested, but hopefully enough of a patch to let the others get cracking on XPR-40.

Jacques Morel - 01/Sep/05 03:17 AM
The patch hasn't been fully applied yet.